As a subcontractor, submit your RFIs directly to your General Contractor on system

JD Williams avatar
Written by JD Williams
Updated over a year ago

Pre-requisites

You must be a user in a Subcontractor workspace type to create and submit Sub RFIs.

Process

  1. Navigate to RFIs from the left-hand menu and click + Add New RFI

  2. Fill out the required fields and specify any relevant information

    1. Note: your specified RFI Manager will receive the RFI when you click Submit

  3. You can propose a solution, indicate any cost or schedule impacts, and add references such as drawing sheets or files

Notes:

If you save the RFI as draft, the RFI will only be visible to you and users within your workspace who have access to your project

If you submit the RFI, it will become visible to the RFI Manager and users within the RFI Manager's workspace who have access to that project