Skip to main content
Updating the Schedule

Modify dates, manage task progress, or update activity connections on the Schedule module!

JD Williams avatar
Written by JD Williams
Updated over 3 weeks ago

Overview

INGENIOUS.BUILD simplifies the management and tracking of construction activities, offering powerful tools that allow users to efficiently update, monitor, and adjust key activity parameters throughout the project lifecycle.


Process

Updating the Schedule

In the General Information tab we can update these activity fields:

  1. Name: Update the activity name.

  2. Start Date: Edit start date.

  3. End Date: Edit end date.

  4. Category: Assign a construction category to an activity.

  5. Working Days: Edit the activity duration.

  6. Progress: Modify the advancement of an activity by adjusting its percentage.

  7. Responsible Party: Assign a responsible party to an activity.

  8. Type: Change activity to milestone.

  9. Tasks: Create a task for an activity (Publish the schedule to add a task).


Connected Activities

Update the activity relationship with predecessors and successors.


Update Progress

  1. Click on the activity.

    1. Review the start date and duration.

  2. Update the activity connection. Click the Edit icon on the right side of the Connected Activity.

    1. Review the predecessor and successor.

    2. Review Connection Type - Finish to Start (FS), Start to Start (SS), Finish to Finish (FF), & Start to Finish (SF).

  3. Float: Add or Remove float of a schedule.


Milestones

You can set a milestone by setting the Working days to '0' or select the toggle type to milestone in the general information tab.



See Also:

Did this answer your question?